Appendix A: Powerwall+ and Powerwall 3 Permanent Non-Export

Overview

Where required by utilities, Powerwall+ and Powerwall 3 can be placed in a permanent non-export mode. This means that in the following scenarios, Powerwall+/Powerwall 3 will curtail solar to prevent power from being exported back to the grid:

  • The battery is fully charged and more solar is being produced than the system is consuming
  • Solar is being produced at a higher rate than the battery can charge at, e.g. 7.6kW of solar on a 5kW battery

This feature is available beginning with Powerwall software version 22.18. One important note is that, in a Powerwall+ or Powerwall 3 system, Powerwall+/Powerwall 3 is the only solar inverter capable of curtailing solar as described above. As such, Powerwall+/Powerwall 3 is referred to as “controlled solar.” Third party solar inverters cannot be controlled by the Powerwall system Site Controller in the same manner and are referred to as “uncontrolled solar.”

This document describes three possible permanent non-export configurations: one with exclusively controlled solar, one with uncontrolled (third party) solar that is allowed to export solar to the grid, and one with uncontrolled (third party) solar that is not allowed to export solar to the grid.

Install Metering for a Permanent Non-Export System

Metering in a permanent non-export system is essentially the same as in any Powerwall system:

  • Site metering must capture all loads and generation, including non-backup loads
  • Solar metering must capture all solar generation, including third party solar inverters

In addition to the Powerwall system metering, any third party solar inverter also requires its own Site meter if it is configured for non-export. Third party Site metering should follow the third party inverter’s installation instructions and should not be modified by the Powerwall system.

The following examples illustrate some common metering configurations for a permanent non-export system.

Example 1: Powerwall 3 Permanent Non-Export System with Only Controlled Solar

Energy to be Metered Meter CT(s) Meter Configuration
Site loads Backup Switch Backup Switch (not shown in diagram) Preconfigured as Meter Z: Site
Powerwall 3 Solar Generation Powerwall 3 integrated energy meter N/A N/A
Powerwall+ Solar generation Factory-installed Neurio meter Factory-installed Neurio 200 A CT Meter paired with Powerwall+ and CT field-configured as Neurio Meter: SolarCTx2

Example 2: Permanent Non-Export System with Uncontrolled Solar

Energy to be Metered Meter CT(s) Meter Configuration
Site backup loads Backup Gateway 2 Meter X Backup Gateway 2 Meter X (not shown in diagram) Preconfigured as Meter X: Site
Site non-backup loads Backup Gateway 2 Meter Y Field-installed Tesla 100 A CTs Field-configured as Meter Y: Site
Powerwall+ Solar generation Factory-installed Neurio meter Factory-installed Neurio 200 A CT Meter paired with Powerwall+ and CT field-configured as Neurio Meter: SolarCTx2
Third party Solar generation Backup Gateway 2 Meter Y Field-installed Tesla 100 A CT Field-configured as Meter Y: SolarCTx2
Third party Site loads Third party Site meter Third party Site CTs Configured by inverter installer to measure Site

Configure a System for Permanent Non-Export Mode

  1. In Tesla One, set Export Permissions to Permanent Non Export on the Operation Settings page.
  2. If the system has standalone solar, uncontrolled by the Powerwall system, determine whether the solar inverter is allowed to export and if that solar inverter is configured with its own controls to prevent export.
    1. If it is allowed to export solar, toggle Solar export limitation to No.
    2. If it is not allowed to export solar, and is configured with its own non-export controls, toggle Solar export limitation to Yes.
      Informational PurposesAn informational icon, calling your attention
      Note
      This provides the Powerwall system with the knowledge that it needs to regulate a small amount of import power to prevent the standalone non-export solar inverter from curtailing. This ensures the best overall system performance for these systems that have two devices both responding to site power measurements.
  3. Take screenshot of this page and the system Summary page after completing commissioning. These will be required as part of the interconnection submission.