Incorrect Current Transformer Location
Warning
Before installing, disconnecting, and/or adjusting CTs, ensure the
circuits being measured are not energized and the system is completely powered down.
Failure to de-energize the system may compromise operator and equipment
safety.
- Verify the CT is clamped properly around the intended conductor(s).
- Verify the CT is not capturing
any other conductor(s).NoteIf a site has multiple inverter outputs and their conductors are being grouped, ensure every conductor is captured.
In the first example below, the CT captures the (3) L1 conductors for three solar inverters. In the second example, the CT captures (2) solar inverter conductors and (1) hot tub conductor, leaving the third solar inverter conductor uncaptured.
CT Placement for Solar in Downstream Generation Panel
If solar is
in a generation panel where the only conductors are solar, the entire generation
panel can be measured:
- If there are additional 120V loads in the downstream panel, move them all to the same phase (in the example below, they are moved to L2).
- Move the Neurio meter and CTs to the upstream panel and place the CT on the downstream panel feeder, choosing the opposite phase (in the example below, the CT is placed on L1).
- Configure the CT as Solar (1CTx2)