Incorrect Current Transformer Location

Warning IconA warning icon, calling your attention to a possibly risky situation
Warning
Before installing, disconnecting, and/or adjusting CTs, ensure the circuits being measured are not energized and the system is completely powered down. Failure to de-energize the system may compromise operator and equipment safety.
  1. Verify the CT is clamped properly around the intended conductor(s).
  2. Verify the CT is not capturing any other conductor(s).
    Informational PurposesAn informational icon, calling your attention
    Note
    If a site has multiple inverter outputs and their conductors are being grouped, ensure every conductor is captured.

    In the first example below, the CT captures the (3) L1 conductors for three solar inverters. In the second example, the CT captures (2) solar inverter conductors and (1) hot tub conductor, leaving the third solar inverter conductor uncaptured.

    Figure 1. Solar CT Measuring all PV (top) and Solar CT Measuring Partial PV and a Non-Solar Load (bottom)

CT Placement for Solar in Downstream Generation Panel

If solar is in a generation panel where the only conductors are solar, the entire generation panel can be measured:
  1. If there are additional 120V loads in the downstream panel, move them all to the same phase (in the example below, they are moved to L2).
  2. Move the Neurio meter and CTs to the upstream panel and place the CT on the downstream panel feeder, choosing the opposite phase (in the example below, the CT is placed on L1).
  3. Configure the CT as Solar (1CTx2)