Install the Energy Meter
CAUTION
Never perform work
on live circuits. De-energize the electrical panel before continuing.
- Attach the energy meter's
mounting plate to the inside of the electrical panel, and push the meter onto
the plate.NoteThe energy meter requires 8 x 8 x 4 inches of space inside the electrical panel. This clearance allows for the space required for routing wiring to the energy meter.NoteThe maximum distance the energy meter can be installed from the Wall Connector (wired RS-485 connection) is 400 ft (122 m).
- Wire the meter voltage taps:
- Connect the voltage line
harness leads to a dedicated circuit breaker (not exceeding 20A) of
corresponding phase inside the distribution board:
Voltage Harness Port/Wire Color Distribution Board Connection A/Black L1 breaker terminal B/Red L2 breaker terminal C/Blue Capped with wire nut N/White Neutral busbar - Plug the voltage line
harness into the meter.NoteIf a dedicated breaker is not available, the voltage line harness can be spliced to existing breakers if allowed in your jurisdiction.
Figure 1. Voltage Line Harness Wired to Dedicated Breaker (Left) or Spliced to Existing Breaker (Right) NoteThe blue wire of the voltage line harness is capped with a wire nut for split phase installations. This wire is only needed for three-phase installations.
- Connect the voltage line
harness leads to a dedicated circuit breaker (not exceeding 20A) of
corresponding phase inside the distribution board:
- Install the current transformers
(CTs):
- Clip the CTs around Line 1 and Line 2 of the Panel Service
- the
main conductors feeding the panel. NoteEnsure the "Source this Side" label faces away from the breakers, and towards the grid.
Figure 2. CT Orientation in Relation to Power Flow (Label to Face Power Source, in this Case Grid) - Plug the CTs into the
meter:
- The CT measuring Line 1 can be plugged into either Port 1 or Port 4.
- The CT measuring Line 2 must be plugged into Port 2.
NoteIt is critical that each CT have the correct voltage reference. Ensure the CT is plugged into the correct port based on the phase it is measuring.
- Clip the CTs around Line 1 and Line 2 of the Panel Service
- the
main conductors feeding the panel.
- Establish a hardwired RS-485
connection between the Energy Meter and Wall Connector using the included
2-conductor wire harness:
- Plug the provided wire harness into the port.
- Extend the harness leads by splicing 16 AWG shielded twisted pair cable to the harness.
- If applicable, land the drain wire on the ground bar in the panel.
- Locate the terminals on the backside of Wall Connector.
- Land the wire
corresponding to the red lead of the harness to the red port, and the
black lead to the white port.NoteThe wiring configuration for RS485 is critical and cannot be reversed after installation, as improper setup may lead to operational failures or equipment damage. Ensure correct polarity and termination during initial installation.
- Manage the communication wires so that they are not pinched when mounting the Wall Connector to the wire box.
- Energize the panel and turn on the circuit breaker(s). The energy meter will chime when it has powered on and the meter LED will illuminate in green.