Make Powerwall 3 Wiring Connections
Make Powerwall 3 PV Power Connections
1 |
MPPT Positive PV inputs: 10-6 AWG (6-16 mm2) |
2 |
MPPT Negative PV inputs: 10-6 AWG (6-16 mm2) |
3 |
Ground terminals: 12-4 AWG (2.5-25 mm2) |
4 | Gather conductors in provided cable tie |
5 | Leave a service loop |
- Jumpers can be used when IMP > 13A. Use jumpers to allow a single MPPT to intake strings with a total IMP up to 26A
- Land the combined circuit (2 strings in parallel = 1 circuit) or string with
IMP greater than 13A in the terminal and connect the jumper
from:
- MPPT 1 to MPPT 2
- MPPT 5 to MPPT 6
- MPPT PV inputs 3 and 4 cannot be combined and are closed from the factory
- Only use the Powerwall 3 MPPT jumpers (Tesla P/N 1784893-xx-y) provided in the Powerwall 3 accessory bag
- Do not use jumpers on Solar Roof jobs - you cannot parallel more than two strings so combined circuit IMP will always be less than 13A DC
- Ensure each jumper is fully seated in the connector!
Connect Powerwall 3 to the Backup Switch / Backup Gateway 2 / Gateway 3
1 |
CN- (CAN LO): 24-16 AWG (0.2-1.5 mm2) |
2 |
CN+ (CAN HI): 24-16 AWG (0.2-1.5 mm2) |
3 |
GND: 24-16 AWG (0.2-1.5 mm2)* |
4 |
12V+: 24-16 AWG (0.2-1.5 mm2)* |
5 | Strip back the cable jacket so that the wires lay flat, leaving room to install the front cover. Route the cable through the lower left tab |
6 | Leave a service loop |
*18 AWG is the recommended minimum wire gauge due to potential voltage drop on long wire runs.
Make Powerwall 3 AC Power Connections
Connect Powerwall 3 to a 60A breaker.
1 |
N / L2 / L1: 10-4 AWG (6-25 mm2) |
2 |
Ground terminals: 12-4 AWG (2.5-25 mm2) |
3 | Gather conductors in provided cable tie |
4 | Leave a service loop |
Fuse Type | Manufacturer | Part Number |
---|---|---|
Fast-Acting Fuse, Class RK1, >= 250VAC, CLF | Littelfuse | KLNR60 |
Eaton / Bussmann | KTN-R-60 | |
Mersen / Ferraz Shawmut | A2K60R |
Install System Shutdown Switch Where Required
1 |
Rapid Shutdown IN: 24-16 AWG (0.2-1.5 mm2) |
2 |
Rapid Shutdown OUT: 24-16 AWG (0.2-1.5 mm2) |
3 | Remove RSD jumper when installing System Shutdown Switch; otherwise, leave installed |
4 | Strip back the cable jacket so that the wires lay flat, leaving room to install the front cover. Route the cable through the lower left tab |
5 | Leave a service loop |
6 | Connect the RSD wiring to a suitable DC switch (see the Powerwall 3 with Backup Gateway 2, Backup Switch, or Gateway 3 installation manual for full details) |
Install Ferrite Cores / Metal PV Shield
For Powerwall 3 P/N 1707000-00-J and higher, install the metal PV shield and LV ferrite core:
1 | Low voltage harness ferrite |
2 | Metal PV shield |
For Powerwall 3 P/N 1707000-00-H and lower, install the (3X) ferrite cores:
1 | AC ferrite |
2 | PV ferrite |
3 | Low voltage harness ferrite |
Secure each ferrite with its provided cable tie.
Important Notes on Wire Routing
1 |
|
2 |
|
3 |
|
1 |
|
2 |
|
3 |
|
1 | AC wires are routed across the front of the enclosure which would prevent the front cover from being installed |
2 |
|
1 |
|
1 | AC and PV wiring do not have service loops |
2 | Communication cable is routed from top; no drip loop creates the potential for water to follow the cable and drip into the wiring terminals |
3 | AC and PV wires are not secured with cable ties |