Confirm Device Setup
After commissioning Powerwall 3 using the Powerwall 3
Device Setup Guide, confirm the following.
- Confirm the system is on and operational
- Confirm Powerwall 3 is updated to the latest firmware version
- All units (Powerwall 3 and Powerwall 2 units) are
visible on the Devices
page
- Select each unit to confirm it displays the correct line voltage
- Confirm the system is charging / discharging normally
- If Powerwall 3 is connected to solar,
confirm the connected strings are visible and solar production is within the
expected voltage rangeNoteIf moving existing PV strings to connect them to Powerwall 3, ensure all wiring meets current regulations.
- If the system includes AC-coupled solar, confirm the solar is metered and solar production is within the expected voltage range
- Confirm all meters are reporting correctly, and there are no errors or alerts present
Troubleshooting Common Issues
| Symptom | Likely Cause | Fix |
|---|---|---|
| Powerwall 2 not visible after commissioning Powerwall 3 | Communication wiring issue |
|
| Only the Powerwall 3 capacity is displayed |
|
|
| Powerwall 2 is not responsive to its product switch | 12V and GND wires are swapped in communication wiring from Powerwall 2 to Powerwall 3 |
|
| Power is oscillating when system is off-grid | Frequency shift mismatch between Powerwall 3 and Powerwall 2 |
|