Perform Device Setup
-
Connect to Powerwall 3 using the Tesla One app and
perform device setup.
NoteAfter turning on the unit, allow 2 - 3 minutes for the Wi-Fi signal to begin broadcasting.
-
Navigate to the Networking tab and
connect the unit to the customer's Wi-Fi, if available.
Refer to Configure Internet Connection section in the
Powerwall 3 Device Setup Guide for more information.
-
On the Software tab, check for
software updates and download any available updates.
NotePowerwall 3 must be updated to software version 26.26 or later to commission a system with Powerwall 2 units.
-
Navigate to the System tab and verify
that all units are present. If the communication is not established, inspect the
communication wiring between the units. See Connect Powerwall 3 to Existing System for communication wiring
diagrams.
-
Set the Powerwall's maximum
power/current output using instructions in Configure Powerwall 3 Maximum Power / Current
Output.
This value must be set to comply with permit requirements. Refer to the plan set to determine the correct values.
WarningThis step is critical. Failure to complete it can result in electrical faults in the wiring due to overcurrent. Do NOT start the system before setting this limit. -
Use a paint pen to mark the
configured power output limit on the product label on the left side of the Powerwall 3 unit. Mark the box
corresponding to the limit set.
-
Navigate to the Metering tab to configure
the Tesla Remote
Meter and CTs if installed.
NoteIf Meter Y is used in the Gateway, it does not need to be replaced. Only Neurio meters and CTs must be replaced.
-
Navigate to the Settings tab to set the
grid code and solar installation type. If the site requires additional settings,
set those under the Advanced
Settings option.
Refer to Configure Settings for more information.
- Perform a Backup Test to confirm the system disconnects from and reconnects to the grid as expected, and that all Powerwall units contribute to powering the home when off-grid. Confirm the system is on-grid and successfully displays off-grid during Backup Test. If the Backup Test is not successful, inspect the system wiring. Escalate to Support if needed.
- Perform an E-Stop Test to confirm the System Shutdown Switch is functioning as expected.
-
Complete the Installer Registration as
follows:
-
Complete the Customer Registration as
follows:
NoteCustomer registration is the action that triggers the API call to the cloud, which transmits the new device configuration for the site. This will ensure the customer can see the updated site in their Tesla Mobile App, and the Partner(s) can see the correct device in Powerhub.
-
Start the system.