1.12 |
March 20, 2025 |
- Added note to
Design Considerations that, for
systems with Powershare-capable vehicles and EV chargers in the
backup circuit, the Tesla-branded EV charger must be considered
a generation source in backfeed calculations
|
1.11 |
March 7, 2025 |
|
1.10 |
October 24, 2024 |
- Updated Design Considerations to reflect that Powerwall 3 can be
configured to have an off-grid maximum continuous discharge
power of 15.4 kW if installed with an 80A breaker and
appropriately sized conductors
|
1.9 |
October 9, 2024 |
|
1.8 |
September 4, 2024 |
|
1.7 |
August 28, 2024 |
Updated Design Considerations and Metering Considerations to
reflect Tesla Remote Energy
Meter as an option for
metering non-backup loads and/or AC-coupled solar |
1.6 |
July 25, 2024 |
- Updated Design Considerations to reflect the required Powerwall 3 circuit
breaker sizes depending on configured maximum current / power
output
- Updated Powerwall 3 DC System Sizing to reflect that DC solar system size should
be sized appropriately if Powerwall 3 is power /
current limited
|
1.5 |
July 2, 2024 |
- Updated System Tie-in to reflect fuse requirements if using a 60A
fuse rather than a circuit breaker for Powerwall 3 overcurrent
protection
- Updated Powerwall 3 Solar with warning that where it is allowable to
install only (1) MCI per string, MCI-1 must be used
|
1.4 |
May 24, 2024 |
|
1.3 |
May 7, 2024 |
- Added note to
Design Considerations that Backup Switch is not certified for
installation in Canada
- Updated Powerwall 3 DC System Sizing with recommendation to distribute the DC PV
system across all Powerwall 3 units when
installing multiple units
|
1.2 |
April 25, 2024 |
Updated Design Considerations, Metering Considerations,
and Backup Switch / Backup Gateway 2 / Gateway 3 Tie-in to include Gateway 3 as an Islanding
Controller option |
1.1 |
March 21, 2024 |
|
1.0 |
January 31, 2024 |
Initial publication |