Configure Backup Gateway 2 Primary (Meter X)

Backup Gateway 2 Meter X has built in CTs, with the following voltage references:
  • CT 1: L1
  • CT 2: L2
  • CT 3: L3
  1. Select Gateway Primary Meter X and select what the CTs are measuring from the Location dropdown.
    Informational PurposesAn informational icon, calling your attention
    Note
    Meter X CTs can only be configured as a single location, e.g. all CTs are Site.
    • Site: Select when the incoming supply conductors are connected to the Meter X CTs to measure Site.
    • None: Select when the Meter X CTs are not being used.
  2. Review the vitals for each CT (voltage, current, and power factor) to confirm they have been installed and configured correctly.
    Informational PurposesAn informational icon, calling your attention
    Note
    The live power flow and current readings are available for each CT in real time, as well as an overview of all meters and CT settings, in the Metering tab.