Tesla Remote Energy
Meter is
connected to the system Site
Controller wirelessly (any Site Controller) or via an RS-485
wiring harness (Powerwall 3 or
Backup Gateway 2 only).
Figure 1. Location of
RS-485, AC, and External Antenna Terminals
At the time of publication, Tesla Remote Energy
Meter has (3) CT
terminals:Figure 2. Location of CT Terminals
CT4 functionality will be available at a later date.
Tesla Remote Energy
Meter LED
Tesla Remote Energy
Meter has an LED
which indicates the following status:
Solid green ON
Powered and operational
Figure 3. Tesla Remote Energy
Meter LED
Location
About Voltage Taps and Current Transformer
Connections
The Tesla Remote Energy
Meter functions
by measuring voltage (by voltage tap) and current (by Current
Transformer, or CT) at key locations in the system. For the meter to
function correctly, the following are critical:
The Tesla Remote Energy
Meter
voltage line harness leads must be connected to the
correct phases.
The CTs
must be placed around conductors of the correct
phase:
CT1 = L1
CT2 = L2
CT3 = L2
Install the Tesla Remote Energy Meter and CTs describes
how to perform these steps correctly, but the following diagrams
illustrate some high level correct and incorrect meter / CT
installations.
Figure 4. Correct Meter
and CT InstallationFigure 5. Incorrect CT
Installation - CTs are Measuring Incorrect PhasesFigure 6. Incorrect
Meter Installation - Main Breaker Swapped Busbar Phases,
Resulting in Voltage Line Harness Being Wired
IncorrectlyFigure 7. Incorrect
Meter Installation - Installer Skipped a Breaker Pole,
Resulting in Voltage Line Harness Being Wired
Incorrectly