Install the Tesla Remote Energy Meter and CTs
Plan Meter and CT Locations
Before installing the meter and/or CTs, ensure none of the following maximum distances are exceeded:
Distance to Measure | Wiring Option | Tesla P/N (if applicable) | Maximum Distance |
---|---|---|---|
Meter to Point of Measurement | CT lead only | 2033376-xx-y | 1.5 m (59 in) |
If additional length is required: CT extension (3.5 m (138 in) long) | 2060713-xx-y | 8.5 m (335 in) (CT extension (3.5 m) + CT extension (3.5 m) + CT lead (1.5 m) = max 8.5 m) | |
Meter to Site Controller (RS-485 wired connection) | RS-485 harness | 2045794-xx-y | 1.2 m (4 ft) |
If additional length is required: 24 - 16 AWG (0.2 - 1.5 mm2) communication wiring | Not applicable (wiring supplied by installer) | 50 m (164 ft) | |
Meter to Breaker | Voltage Harness | Not applicable (included in the kit) | 600 mm (23.6 in) |
If additional length is required: 16-10 AWG (1.5 - 6 mm2) AC wiring | Not applicable (wiring supplied by installer) | To maintain accuracy for revenue grade metering (RGM), keep the meter within 61 m (200 ft) of its breaker when using 14 AWG (2.5 mm2) wire |
Install the Meter
- Using the screws
provided in the meter kit, attach the meter to the inside of
the main distribution board or to another surface.
- Connect the voltage line harness
leads to a dedicated 15A two pole circuit breaker:NoteIf unsure of the panel phases, see Troubleshooting: Identifying Breaker Phase.
- Black Wire: Connect the black wire to L1
- Red Wire: Connect the red wire to L2
- Blue Wire: If using the CT 3 port, splice the blue wire with the red L2 wire as shown below; otherwise cap the blue wire
- White Wire: Connect the white wire to the Neutral busbar
NoteIf a dedicated circuit breaker is not available, the voltage line harness can be spliced to existing breakers.NoteFor the Remote Energy Meter to function properly, the voltage line harness leads must be connected to the correct breaker phases. The following are common reasons for the voltage line harness being miswired to the incorrect phases: - Plug the voltage line harness into the meter (see Location of RS-485, AC, and External Antenna Terminals).
Install the CTs
- Plug the
CT into the corresponding CT terminal on the
meter.
- Pinch the
CT to open it, then close the CT around the
conductor(s) being measured.NoteEnsure the CT is installed so that the side with white text on the CT housing pointing toward the power source (service entrance / grid for Site CTs, solar inverter for Solar CTs). Always verify CTs are in the correct orientation by observing power flow in the Tesla One app.
Figure 1. CT Orientation in Relation to Power Flow
Connect Tesla Remote Energy Meter to Powerwall 3
Connection Option 1: Connect Tesla Remote Energy Meter via Wi-Fi:
- Drill a ¼-inch (6 mm) hole in the bottom of the enclosure.
- Route the provided antenna extender through the bottom of the enclosure as shown below.
- Thread the provided lock washer and nut onto the extender, then thread the antenna onto the end of the extender. Secure the antenna against the bottom of the enclosure.
Meter configuration, including pairing the meter via Wi-Fi must be performed during commissioning in the Tesla One app. See Configure Wi-Fi Connected Tesla Remote Energy Meter for commissioning instructions.
Connection Option 2: Wire Tesla Remote Energy Meter via RS-485:
Meter and CT(s) configuration must be performed during commissioning in the Tesla One app. See Configure Wired Tesla Remote Energy Meter for commissioning instructions.