Multiple Powerwall 2/Powerwall+ Units to Powerwall 3 Upgrade
Overview
This procedure outlines the steps for upgrading a site with multiple Powerwall 2/Powerwall+ units to a multi-Powerwall 3 with Expansion site.
| Existing Equipment | Replacement Equipment | Scope of Work | Current / Power Output Setting |
|---|---|---|---|
| 2 Powerwall 2 units | 1 Powerwall 3 with 1 Expansion | Remove 30 A circuit, rework circuit to a single 60 A breaker | 41.7 A (10 kW) |
| 3 Powerwall 2 units | 1 Powerwall 3 with 1 Expansion | Remove a 30 A circuit, rework circuit to a single 60 A breaker | 41.7 A (10 kW) |
| 1 Powerwall 3 | Reuse an existing 30 A circuit | 24 A (5.8 kW) | |
| 4 Powerwall 2 units | 1 Powerwall 3 with 1 Expansion | Remove 30 A circuit, rework circuit to a single 60 A breaker | 41.7 A (10 kW) |
| 1 Powerwall 3 with 1 Expansion | Remove 30 A circuit, rework circuit to a single 60 A breaker | 41.7 A (10 kW) | |
| 1 Powerwall+ and 1 Powerwall 2 | 1 Powerwall 3 | Reuse the 30 A circuit | 24 A (5.8 kW) |
| 1 Powerwall 3 | Reuse the 50 A circuit | 32 A (7.6 kW) | |
| 1 Powerwall+ and 2 Powerwall 2 units | 1 Powerwall 3 with 1 Expansion | Remove 30 A circuit, rework circuit to a single 60 A breaker | 41.7 A (10 kW) |
| 1 Powerwall 3 | Reuse the 50 A circuit | 32 A (7.6 kW) | |
| 2 Powerwall+ units | 2 Powerwall 3 units | Reuse both 50 A circuits | 32 A (7.6 kW) |
If the site has a single Powerwall 2/Powerwall+ to be swapped, refer to the appropriate procedure below:
Prerequisites
- Confirm the original site is visible in Powerhub
- If the swap is being completed by a subcontractor company, ensure the site has been shared with that subcontractor company's Powerhub instance. See Site Sharing in the Powerhub User Manual for instructions to share a site
- Ensure the updated planset is available (indicating that a site redesign was completed). The new site design should be compliant with all existing permits, or re-permitted according to the new design
Hazards
Safety and PPE
- Safety glasses (ANSI Z87.1 or EN 166)
- Cut-resistant gloves (ANSI Cut Level 3 or EN 388 Level C)
- Safety rated shoes with leather upper
General Equipment
- Paint pen
Remove
- Complete the Powerwall 2 Lockout/Tagout or Powerwall+ Lockout/Tagout de-energize the system.
-
Follow the steps below to remove all
the Powerwall units on the site.
CAUTIONALL Powerwall 2 or Powerwall+ units must be replaced, as Powerwall 3 is not compatible with older generations of Powerwall. A site cannot include a mix of these.
- If replacing a Powerwall+, follow the Powerwall+ Solar Assembly Removal procedure to remove the PVI portion of the system from the wall.
- Follow the Removing Powerwall 2 procedure procedure to remove the standalone Powerwall 2 units and the battery portion of the Powerwall+ units.
-
Remove the screws securing the
Powerwall mounting bracket to the wall.
Remove the mounting bracket and clean the wall surface from any sealant or dirt.
- Patch the holes created from the mounting bracket hardware using a method suitable for the wall surface.
-
Remove the conduit fittings and
determine the changes needed in the conduit run to accommodate the new Powerwall system.
In most multi-unit installations, the total number of AC connections will be reduced by
using DC Expansion units.
In most cases where the run is short, the conduit should be removed and new conduit should be run.
In cases where the conduit can be reused or extended, make sure that the fittings are appropriate and all the connections are compliant with local code.
Seal any knockout holes left by removed conduit using the appropriate plugs and ensure the seal is watertight.
Install
-
Use the guidelines below to plan the
installation locations of the new units, which generally should mirror the locations of
the previous Powerwall units.
-
Follow the instructions in Powerwall 3 Installation Manual with Backup Gateway 2 to install the new Powerwall 3 and
Expansion units.
-
If a Rapid Shutdown Device (RSD) is
connected to the Gateway 2, it must be moved to the Powerwall 3.
Follow the instructions in STEP 8: Install System Shutdown Switch Where Required in the Powerwall 3 Installation Manual to switch the RSD from the Gateway to the Powerwall 3. The jumper should be removed from the Powerwall 3 and installed in the RSD port of the Gateway 2, from which the switch wire was removed.
NoteThe RSD may need to be replaced if multiple Powerwall 3 units are being installed, as the switch requires a dedicated terminal for each Powerwall in the system. -
Once all conductors are installed,
follow these steps to commission the new unit.
NoteDo NOT complete the Powerwall 3 commissioning procedure outlined in the Powerwall 3 Install Manual. Instead, use the steps provided below which detail several deviations from the standard commissioning procedure.
-
Turn on all the Powerwall 3 switches
and connect to the leader Powerwall 3 using the Device Setup interface in Tesla One
app.
NoteAfter turning on the unit, allow 2 - 3 minutes for the Wi-Fi signal to begin broadcasting.
-
Navigate to the Networking tab and connect the unit
to the customer's Wi-Fi, if available. Refer to Configure Internet Connection section in the Powerwall 3 Quick Guide for more
information.
-
On the Software tab, check for software
updates and download any available updates.
-
Navigate to the System tab and verify that the
Gateway is communicating with the Powerwall 3 without any errors. If the communication
is not established, inspect the CAN wiring between the units.
Verify that all installed units are present and displaying no errors. If any units are missing or showing any errors, troubleshoot the issue before proceeding.
Refer to the Check Connected Devices page for more information.
-
If applicable, set the Powerwall's
maximum power/current output using instructions in the Configure Powerwall 3 Maximum Power / Current Output section.
This value must be set to comply with permit requirements. Refer to the site design to determine the correct values.
WarningThis step is critical. Failure to complete it can result in electrical faults in the wiring due to overcurrent. Do NOT start the system before setting this limit. -
Document the configured limit on the
product label on the left side of the Powerwall unit. Use a paint pen to mark the box
corresponding to the limit set.
-
Navigate to the Metering tab to confirm the
meter(s) are configured correctly. Powerwall 3 only supports Tesla Remote Meters or
wired meters, so any third-party meters, such as Neurio meters, must be replaced with a
Tesla Remote Meter.
Replace meters as necessary and configure them in the Metering tab using the instructions in the Configure Meters and CTs section.NoteReplacing a meter with a Tesla Remote Meter is common at sites with AC-coupled solar or non-backup loads. Follow this guidance to correctly set up the meters: Install Tesla Remote Energy Meter and CTs.NoteIf Meter Y is used in the Gateway, it does not need to be replaced.
-
Navigate to the Settings tab to set the grid code
and solar installation type. If the site requires additional settings, set those under
the Advanced Settings option.
Refer to Configure Settings for more information.
-
Complete the Installer
Registration as follows:
-
Complete the Customer Registration as follows:
NoteCustomer registration is the action that triggers the API call to the cloud, which transmits the new device configuration for the site. This will ensure the customer can see the updated site in their Tesla Mobile App, and the Partner(s) can see the correct device in Powerhub.
-
Start the system.
-
Before leaving the site, inform the
homeowner that their unit has been replaced with a Powerwall 3, and that the device
configuration will update overnight. They will see the new data and can control their
new Powerwall 3 starting the following morning.
Additionally, advise the customer that some app settings might have been reset with the swap and to check their configurations if they have been changed from default values.
Confirm Site Updates in Powerhub
- Confirm the new Powerwall 3 now appears in the Devices list in Powerhub
- The new Powerwall 3 will appear instantly after registration
- Note that Powerhub and the customer's Tesla App will not display data (telemetry or settings info) from the new Powerwall 3 right away. This data will appear after the overnight sync
- The new Powerwall 3 will appear instantly after registration
- Note that the old Powerwall 2 will still appear in the Devices list
- Powerhub will consider these devices "Deactivated" after 30 days of no communication
- Note that this will not impact the customer's app experience, telemetry, or ability to control their Powerwall 3
- Once the 30-day period has passed and the Powerwall 2 device(s) are automatically deactivated, they will no longer appear in the Devices list in Powerhub