Incorrect Current Transformer (CT) Assignment
Ensure all CTs are assigned:
Meter | CT | Default Setting | Other Options |
---|---|---|---|
Powershare Gateway (Meter Z) | Site CT1 (L1) and Site CT2 (L2) | Site | None: Used when the CTs are not being used |
Backup Switch (Meter Z) | Site CT1 (L1) and Site CT2 (L2) | Site | None: Used when the CTs are not being used |
Tesla Remote Energy Meter |
CT1 (L1) |
None: Used when the CTs are not being used | Solar: Used when CTs are installed on conductors (both L1 and L2) to measure Solar. |
Solar RGM: Used to measure Solar when revenue-grade metering (RGM) is required. Select this option when measuring Solar for SREC.2 | |||
Site: Used when CTs are installed on conductors (both L1 and L2) to measure Site. |
1Tesla Remote Energy Meter does not have CT4 functionality at the time of publication.
2If using a single CT to measure Solar or Solar RGM, toggle on 1CTx2 in the CT Modifiers. This will prompt the software to double the output from the CT to calculate total Solar output.
If using a Remote Energy Meter, ensure the correct Current Transformer type is set. The default Current Transformer type is the 200 A Current Transformer.