Site Requirements
Stacked multi-Powerwall systems must be floor-mounted, with all units installed on a structurally sound flat surface that supports both feet of each unit. They must also be anchored to an adjacent wall which must be capable of supporting the lateral load of the Powerwall stack.
A maximum number of 3 floor-mounted Powerwall units may be joined together with two Powerwall Stack Kits. For systems with more than 3 Powerwalls, separate groups of 3 units should be assembled, with each group of 3 attached to a wall.
For complete Powerwall Mechanical Specifications and Site Requirements, see Site Requirements and Pre-Install Guidance.

Note
Powerwall meets the unit level
performance criteria of UL 9540A, allowing Powerwall to be stacked front to back as
long as the clearance requirements defined in this manual are followed to allow for
air flow around the units.