STEP 9: Install Energy Metering
Before you start, see Energy Metering to find the available metering options and the example metering diagrams.
For Backup Gateway 2 Primary Meter X, there is no additional step required to install the meter or CTs as they are integrated in Backup Gateway 2. For Backup Gateway 2 Secondary Meter Y, Tesla 100A CTs must be installed and connected to the Meter Y CT terminals (see Install Tesla 100 A CTs for the installation instructions).
Depending on the site layout, it may not be possible to use the Backup Gateway 2 internal meters. Tesla Remote Energy Meter and Tesla 200A CTs can be installed when needed (see Install Tesla Remote Energy Meter and CTs for the installation instructions).