Install Tesla 100 A CTs
Warning
Before installing, disconnecting, and/or adjusting CTs,
ensure the circuits being measured are not energized and the system is completely
powered down. Failure to de-energize the system may compromise operator and
equipment safety.
- Plug the Tesla 100 A CT into the terminal in the Backup Gateway. Ensure the connector is fully seated in the terminal.
- Clamp the CT around the conductor to be measured.
Tips
- When
metering 3-phase solar inverters, install CTs on L1, L2, and L3 output of the
solar inverter AC circuit. NoteA single CT can be installed on L1 and connected to CT1 port to measure the solar power from a 3-phase solar inverter. Make sure to toggle 1CTx3 button to the ON position when configuring the CT during commissioning; the software triples the power measured by the CT. To ensure that the total power output calculated by software is correct, the solar power must be converted by a balanced 3-phase solar inverter, which distributes power evenly between the three phases.
- Ensure CTs are facing the proper direction as indicated on the label. A CT will show negative current if installed backwards.