Install the Backup Switch
Applying oxide-inhibiting electrical joint compound to all
four meter socket jaws is recommended prior to installing the Backup Switch. Follow the
manufacturer's guidance when applying.
Warning
Even though circuits
have been turned off and are not under load, conductors may still be live. Wear all
electrical PPE as defined in Required Tools.
-
Align the Backup Switch with the
meter socket and, using a rocking motion, plug it into place.
NoteThe Backup Switch must be fully inserted to ensure the system is grounded.
-
For ring type meter
sockets: Install the sealing ring to secure the Backup Switch to the
meter socket.
NoteEnsure the sealing ring is oriented such that the FRONT arrow etched into the ring faces toward the meter, and not the panel. The front wall of the sealing ring is shallower than the rear wall to match the profile of the Backup Switch; thus, the sealing ring cannot be installed if it is not oriented correctly.NoteTesla recommends installing a cable tie or similar locking means on the sealing ring(s) to discourage tampering with Backup Switch.
-
For ringless meter
sockets: Install the meter socket cover.