STEP 11: Turn On and Commission the System

Warning IconA warning icon, calling your attention to a possibly risky situation
Warning
Confirm the Powerwall 3 Enable switch and AC breaker are both OFF before terminating any wires at Powerwall 3, or before altering / removing any wiring.
Confirm the following steps have been completed BEFORE turning on the Powerwall 3 Enable switch and energizing the AC circuit: Any damage to Powerwall 3 resulting from improper wiring will not be covered under warranty, and it will be the responsibility of the installer to replace the unit. See Avoiding Out-of-Warranty Damage to Powerwall 3 for more information.

Prepare the System for Commissioning

Installation Scenario Actions
Powerwall Installation Complete? Solar Installed? Backup Switch Installed? Does Utility / AHJ allow the system to run pre-PTO?* Enable (On / Off) Switch Powerwall 3 Breaker Commissioning
Yes Yes Yes No Leave the Enable switch OFF Leave the Powerwall 3 breaker CLOSED (ON) See Commission the System After Powerwall and Solar Installation
Yes Yes Yes Yes Leave the Enable switch ON Leave the Powerwall 3 breaker CLOSED (ON) See Commission the System After Powerwall and Solar Installation
Yes N/A (applicable whether solar is installed or not) No Yes Leave the Enable switch ON Leave the Powerwall 3 breaker CLOSED (ON) Commission prior to Backup Switch installation
Yes N/A (applicable whether solar is installed or not) No, and commissioning could not be completed as defined above N/A (system not ready to be turned on) Leave the Enable switch OFF Leave the Powerwall 3 breaker CLOSED (ON) Commissioning cannot be completed at this time (schedule a second site visit to complete)
Yes No Yes N/A (system not ready to be turned on) Leave the Enable switch ON Leave the Powerwall 3 breaker CLOSED (ON) See Commission the System Ahead of Solar Installation
Yes, but commissioning could not be completed (could not resolve errors with troubleshooting) N/A (applicable whether solar is installed or not) Yes N/A (system not ready to be turned on) Leave the Enable switch OFF Leave the Powerwall 3 breaker CLOSED (ON) Commissioning cannot be completed at this time (schedule a second site visit to complete)
No (no AC service, install crew unable to complete, etc.) No No N/A (system not yet installed) Leave the Enable switch OFF Leave the Powerwall 3 breaker OPEN (OFF) Commissioning cannot be completed at this time (schedule a second site visit to complete)

*In some cases, the Utility or AHJ may not allow the system to be turned on at the time of install. Instead, once PTO is received the customer can be notified to turn their system on.