STEP 11: Turn On and Commission the System
Warning
Confirm the Powerwall 3
Enable switch and AC breaker are both OFF before terminating any wires at Powerwall 3,
or before altering / removing any wiring.
Confirm the following steps have been
completed BEFORE turning on
the Powerwall 3 Enable switch and energizing
the AC circuit:
- MCIs have been installed in each PV string as described in Install Mid-Circuit Interrupters in PV Array
- Each PV string has been tested as described in Test PV Strings with MCIs
Prepare the System for Commissioning
| Installation Scenario | Actions | ||
|---|---|---|---|
| Installation Complete? | Does Utility / AHJ allow the system to run pre-PTO?* | Enable (On / Off) Switch | Powerwall 3 Breaker |
| Yes | Yes | Leave the Enable switch ON | Leave the Powerwall 3 breaker CLOSED (ON) |
| Yes | No | Leave the Enable switch OFF | Leave the Powerwall 3 breaker CLOSED (ON) |
| Yes, but commissioning could not be completed (could not resolve errors with troubleshooting) | N/A (system not ready to be turned on) | Leave the Enable switch OFF | Leave the Powerwall 3 breaker CLOSED (ON) |
| No (no AC service, install crew unable to complete, etc.) | N/A (system not yet installed) | Leave the Enable switch OFF | Leave the Powerwall 3 breaker OPEN (OFF) |
*Leaving a Powerwall 3 system on and operating is preferred and recommended. The system will automatically be in a temporary Non-Export Self-Powered Mode while waiting for Permission to Operate (PTO). This allows the customer to immediately use the system for backup and start reaping the financial benefits of their system.
When PTO is received from the utility, there are two methods to enable grid
export:
- Customer: Have the customer change the Permission to Export setting to Yes in their app.
- Installer: Using the Device Setup interface via Powerhub, change the Enable Exports setting to Enabled.
Commission the System
- Close the AC circuit breaker for Powerwall 3 .
- Turn the Powerwall 3 switch ON.
- Launch the Tesla
One app.NoteEnsure Tesla One is updated to version 7.9.1 or greater, or install Tesla One if using for the first time.
- Navigate to Device Setup to begin
commissioning. NoteSee the Powerwall 3 Device Setup Guide for complete instructions.
- Select Scan and scan the Powerwall 3 QR label to connect to
the TeslaPW Wi-Fi network.
- Scan the QR label on
the Powerwall 3 Tesla Asset
Controller (TACO) to commission the system.
- Do not scan the
datamatrix on the side of Powerwall 3
- Scan the QR label on
the Powerwall 3 Tesla Asset
Controller (TACO) to commission the system.
- Address any alerts to complete commissioning.
- If solar is not yet / will not be
installed, skip the PV commissioning steps.
- When commissioning a system with no solar, Powerwall will charge from grid until State of Energy (SOE) is 20%. This is expected behavior.
- When performing the
Backup Test, select Solar is not
expected.
NoteThe Backup Test can be performed during the Backup Switch device update. There is no need to wait for the update to complete before performing the Backup Test. - Leave the system running in Tesla One.
- Leave the Powerwall switch ON and the breaker CLOSED to enable
charging.NoteThe Powerwall 3 On / Off switch has a locking mechanism. When the switch is locked it cannot be turned on. See Powerwall 3 Switch Locking Mechanism for more information.