Install Backup Switch Behind the Utility Meter

      • Remove the Meter
      • Inspect the Meter and Meter Socket
      • Install the Backup Switch
      • Reinstall the Meter
      Parent topic: STEP 4: Install Backup Switch
      • Powerwall 3 Installation Manual with Backup Switch
      • General Warnings and Information
      • Specifications
        • Powerwall 3 Specifications
        • Powerwall 3 Expansion Specifications
        • Mid Circuit Interrupter Specifications (P/N MCI-1) PV Rapid Shutdown Equipment (PVRSE)
        • Mid Circuit Interrupter Specifications (P/N MCI-2) PV Rapid Shutdown Equipment (PVRSE)
        • Backup Switch Specifications
          • Backup Switch Physical Requirements
      • Registering Powerwall 3
      • Powerwall 3 System Overview
        • Powerwall 3 Overview
      • Site Requirements and Pre-Installation Guidance
      • Preparing for Installation
        • In the Powerwall 3 Box
          • In the Powerwall 3 Accessory Bag
        • In the Backup Switch Box
          • In the Backup Switch Accessory Bag
        • Powerwall 3 Service Parts, Orderable Parts, and Accessories
        • Backup Switch Service Parts, Orderable Parts, and Accessory Kits
        • Required Tools
        • Required Supplies
      • STEP 1: Plan the Installation Site
        • Choose a Location that Meets Powerwall 3 Clearance Requirements
        • Plan Powerwall 3 Mounting Configuration
        • Plan Cable Length Between Components
        • Choose Powerwall Cable Entry
        • Plan Amount and Size of Conduit or Raceway
      • STEP 2: Remove Powerwall 3 from Packaging and Transport Using the Powerwall Dolly
      • STEP 3: Wall-Mount Powerwall 3 Using Wall Bracket
      • STEP 4: Install Backup Switch
        • Determine Where to Install Backup Switch
        • Install Backup Switch Behind the Utility Meter
          • Remove the Meter
          • Inspect the Meter and Meter Socket
          • Install the Backup Switch
          • Reinstall the Meter
        • Install Backup Switch in a Standalone Meter Panel
          • Inspect the Meter Panel
          • Install Meter Panel and Backup Switch
        • Connect Powerwall 3 to the Backup Switch
      • STEP 5: Make Powerwall 3 AC Circuit Connections
      • STEP 6: Make Solar PV Connections
        • Install Mid-Circuit Interrupters in PV Array
        • Test PV Strings with MCIs
        • Make PV Power Connections
        • Install MPPT Jumpers (Optional)
      • STEP 7: Install Clamp-on Ferrite Cores / Metal PV Shield
      • STEP 8: Install System Shutdown Switch Where Required
      • STEP 9: Install Energy Metering for the System
      • STEP 10: Complete the Installation
        • Plan Internet Connection for Powerwall
        • Close Wiring Compartments
      • STEP 11: Turn On and Commission the System
        • Commission the System After Powerwall and Solar Installation
        • Commission the System Ahead of Solar Installation
      • STEP 12: Demonstrate the Installation
        • Technical Support
        • Maintenance
      • Appendix A: Powerwall 3 Anchoring Details
        • General Anchoring Notes
        • Powerwall 3 Wall Bracket Anchoring Details for Wall-mounting or Ground-mounting on Approved Foundation
        • Powerwall 3 Wall Bracket Anchoring Details for Stacked Configurations
        • Concrete Pad Details for Ground-mounting Powerwall 3 on Pre-Cast Concrete Pad an Existing Structural Wall
        • Anchoring and Concrete Pad Details for Ground-mounting Powerwall 3 on Poured Concrete with Steel Posts
        • Powerwall 3 Center of Mass
      • Appendix B: Wiring Reference
        • Powerwall 3 AC and PV Wiring
          • Powerwall 3 as a Wiring Raceway (Multi-Unit Installations Only)
        • Tesla Asset Controller (TACO) Low Voltage and Communication Wiring
          • Prepare Ethernet Wiring with RJ45 Connectors
          • Load Shedding Feature
        • Backup Switch Wiring
      • Appendix C: System Wiring Diagrams
        • Backup Switch Wiring Diagrams
      • Appendix D: Solar Rapid Shutdown
        • Rapid Shutdown Initiation
        • Self-Test Function
        • Rapid Shutdown Initiator Label
          • RSD Initiator Label Location
      • Appendix E: Inverter Settings
      • Appendix F: Safety Features
        • Powerwall 3 Switch Locking Mechanism
        • Arc Fault Detection and Protection
        • Ground Fault Protection
        • Protective Earth Impedance Check
        • System LED Behavior
          • Powerwall 3 LED Behavior
          • Backup Switch LEDs
      • Appendix G: Installing Multiple Powerwall 3 Units and/or Expansion Units
        • Electrical Equipment Sizing and Overcurrent Protection
        • Install Multiple Powerwall 3 Units
        • Install Expansion Units with Powerwall 3
          • Install Stacked Expansion Units
          • Wall Mount an Expansion Unit
      • Appendix H: Shutting Down Powerwall 3
      • Appendix I: Servicing Powerwall 3
        • De-Energize Powerwall 3 Before Performing Service
        • Performing a Backup Switch Manual Override
        • Backup Switch Manual Override Switch Positions
      • Appendix J: Revision Log
      • © Tesla 2025