Appendix A: Powerwall 3 Anchoring Details
A1
Ground- or Wall-mount Powerwall 3 with Wall Bracket | Ground-mount Powerwall 3 on Pre-cast Concrete | Ground-mount Powerwall 3 on Poured Concrete with Steel Posts | |
Wall and Foundation | Existing structural wall and existing approved foundation | Existing structural wall and pre-cast concrete foundation | Poured concrete with steel posts |
Seismic Design Category | A, B, C, D, or E | A, B, C, or D | A, B, C, or D |
Max Wind Speed |
180 mph |
180 mph |
180 mph |
Installation Information | Installation instructions | Installation instructions (A10 - A11) | Installation instructions and anchoring details (A12 - A15) |
Anchoring details (A6 - A9) | Anchoring details (A6 - A9) |
The following conditions will require additional site-specific evaluation by the
installing company's structural designer or other qualified person acceptable to the
Authority Having Jurisdiction (AHJ):
- Wind Exposure Category D
- Wind speeds greater than 180 mph
- Poured concrete pad information included in the installation manual are required minimums. Contractors can work with a third party structural designer or other qualified person acceptable to the AHJ for further considerations on the new foundation
- If needed, reference ICC codes and referenced ASCE 7 standards for design criteria