Appendix H: Shutting Down Powerwall 3

Powerwall 3 system shutdown for emergency response or maintenance requires initiation of rapid shutdown, emergency shutdown, and opening of the disconnecting means.

CAUTION
Open all third party solar inverter breakers or handled disconnects before shutting down the Powerwall 3 system.

Safely Shut Down Powerwall 3 for Maintenance or Service

  1. If there is third party solar on-site, turn off the AC breaker for each solar inverter.
  2. If a System Shutdown Switch is present, push it to initiate Rapid Shutdown. If there is no System Shutdown Switch, turn the Enable switch on the Powerwall 3 to OFF.
  3. Open the Powerwall 3 AC circuit breaker.
  4. Wait 30 seconds before proceeding with any work.
    Warning
    Risk of electric shock from stored energy. Wait 30 seconds after disconnecting all sources of supply before proceeding.
  5. Use a lock-out device on the disconnecting means listed in the table below whenever performing work on equipment that is not within sight of the switch.

Rapid Shutdown, Emergency Shutdown, and Disconnecting Means for Powerwall 3

Device PV Rapid Shutdown per NEC 690.12 Emergency Shutdown per NEC 706.15 Disconnecting Means
System Shutdown Switch (Emergency Stop Device) Initiates PV rapid shutdown De-energizes AC output to premises wiring N/A
Powerwall 3 Enable Switch Initiates PV rapid shutdown De-energizes AC output to premises wiring N/A
Circuit Breaker or Handled Disconnect N/A N/A Primary disconnecting means to isolate all ungrounded Powerwall 3 AC circuit conductors from the premises wiring