Remote Energy Meter
Field Tests
- Conduct all CT tests with at least 1 kW of power flowing.
- For each site CT, follow steps to ensure it is in the correct location and
orientation:
- Adjust the Amps/kW slider
to see what the CTs are reading
- Verify the on-screen
values for the CT against the applicable meter (such as the utility
meter)
- Ensure that site CTs are
positive for import, negative for export
- Negative power flow may indicate CT is installed on the wrong phase
- If the “toward source” CT
label is correctly facing the utility meter, but power flow is negative,
a voltage-current mismatch is likely
- Physically move the CT to
the correct phase with the label facing the correct direction.
- Use a handheld clamp or fork meter to verify CT readings.