Check for any red cards in the Configuration Interface, as a red card indicates
a step that must be completed.
Ensure all self-tests passed. To retry self-tests, reset the inverter (using the
Configuration Interface or AC power cycle). If self-tests fail, see “Self-Test
Troubleshooting” section above.
Check AC breaker is on the ON position and there is voltage in the inverter
terminals.
Ensure the number of MPPTs indicated in the Configuration Interface matches the
installation.
Ensure the number of MCIs indicated in the Configuration Interface matches the
installation.