Close the Wiring Compartments and Turn the System On
- Before closing any installed hardware, take photos of the completed wiring in the Powerwall+, Backup Switch, and main distribution board.
- Ensure that all conduit junctions and cable entry points are secure and properly sealed.
- Arrange all wires neatly inside the Powerwall+ wiring compartments.
- Mount the solar assembly door.
- Clean out the solar assembly enclosure and vacuum out any dust.
-
Install the grounding jumper:
- Close the solar assembly door and latch it shut.
- Using a right angle Phillips head screwdriver, tighten the captive screw on the solar assembly door to secure it.
- Use a breaker label sheet to clearly label the circuit breakers.
- Install signage complying with local AHJ requirements at the panel and at the Rapid Shutdown initiator. Depending on the installation, the Rapid Shutdown initiator will be the Powerwall+ Enable switch AND/OR at the System Shutdown Switch. See Appendix E: Solar Assembly Rapid Shutdown for a label example and diagrams of label placement in common system configurations.
- Switch on the AC circuit breaker for Powerwall+.
-
Switch on Powerwall+ by moving the Enable switch on the right side of the unit to the ON position.
CAUTIONAlways leave site with Powerwall+ breaker closed for battery to maintain a base level of charge. Leaving the Powerwall+ disconnected from AC for extended periods increases risk of damage.