Current Transformer Placement

Site (Grid) CTs are placed between the utility meter and the main switch to measure both loads and generation.

Figure 1. CT Placement for Site Metering

For systems that require revenue grade metering, a Solar CT is placed after the solar inverter breaker(s) to measure solar generation.

Figure 2. CT Placement for Solar Metering