Commissioning Pre-Checks
Miswiring
The following installation mistakes can present a safety hazard or cause damage to customer equipment and must
be double-checked before system energization:
- Swapped line & neutral conductors (to the Powershare Gateway, load panels, or Wall Connector.)
- Disconnected / loose neutral (between the Powershare Gateway and load panel, or to individual loads.)
- Swapped neutral / ground
- Incorrectly bonded neutral-ground
- Ensure that all conduit junctions and cable entry points are secure and properly sealed.
Before closing equipment, double check all wiring terminations and torque values.