Request Backup Switch Installation by Southern California Edison (SCE)

Informational PurposesAn informational icon, calling your attention
Note
Download the SCE Backup Switch Approval Documents zip folder from Partner Portal for the latest documents pertaining to installing Backup Switch in Southern California Edison (SCE) territory.
  1. Use the SCE Grid Interconnection Processing Tool (GIPT) to submit an interconnection application.
    Informational PurposesAn informational icon, calling your attention
    Note
    See the SCE Grid Interconnection Processing Tool Application (Powershare) document for an example of a completed interconnection application.
  2. Download and complete the latest revision of the Customer Agreement form from the SCE Meter Socket Adapter Program page.
  3. Submit a Meter Socket Adapter installation application via the dedicated Meter Socket Adapter Online Enrollment Portal (see the Meter Socket Adapter Program user guide for more information).
    Informational PurposesAn informational icon, calling your attention
    Note
    Enter the Interconnection Application Number obtained during Step 1 above when prompted.
Informational PurposesAn informational icon, calling your attention
Note
  • Backup Switch variants with Tesla part number 1624171-95-K or later are compatible for installation in SCE territory. Do not attempt to install any older Backup Switch variant.
  • Ensure Backup Switch was left on site before requesting installation (see Complete Installation for instructions on how to leave Backup Switch)
  • Ensure liquid tight conduit was not used between Powerwall and Backup Switch (they should only be connected via communication wiring per Complete Installation)
Informational PurposesAn informational icon, calling your attention
Note
An installer does not need to be present for the Backup Switch installation appointment.